Start of assembling of Yilu 02 330MW steam turbine

The first set of 330MW condensing steam turbine generator unit for Shandong Longkou Yilu Co. is going to the end of assembly, and to do no-load test ,the 2nd  set of 330MW condensing steam turbine either the contract supplied cylinders and self-manufactured cylinders are completed the machining in the gas turbine workshop. After the assembly of 3 sections of bearing housing and seats, HP section and LP section of cylinders will be put on the assembling platform, thus entering assembling stage of each section. At present, assembling personnel for these sections in the workshop are carrying out assembling work as well as sorting out, to actively create conditions for subsequent rotor alignment , and adjustment of dynamic and static clearances..